The Rapidbuild Process

RapidBuild established in North Wales has been supplying a unique building system to the construction and building trade throughout the UK since 2012.

 
 
 

RapidBuild 15 step process.

The RapidBuild system is a breakthrough innovation in house building. Using all materials from traditional masonry construction, the system simply allows builders to construct houses in a different way, resulting in a considerably faster build and higher quality finish, with all the economic benefits that accrue from the increased productivity.

RapidBuild is a proven concept and thanks to its international patents is different to anything else available on the market. We’re equally at home dealing with single site operations or multi-national blue chips and have a distribution network across the country. This ensures that no matter where you are we have the optimum solution at hand to meet your exact needs. There are Four distinct Phases for a building project: DESIGN PLANNING MANAGEMENT and BUILD. The BUILD Phase consists of a 15 Step Process as detailed here.

The RapidBuild business is a breakthrough innovation in house building. Using all materials from traditional masonry construction, the system simply allows builders to construct houses in a different way, resulting in a considerably faster build and higher quality finish, with all the economic benefits that accrue from the increased productivity.

RapidBuild is a proven concept and thanks to its international patents is different to anything else available on the market. We’re equally at home dealing with single site operations or multi-national blue chips and have a distribution network across the country. This ensures that no matter where you are we have the optimum solution at hand to meet your exact needs. We base our business on a four step process of DESIGN PLANNING MANAGEMENT and BUILD (links to each step as existing website)

Placeholder

Step One


Scaffolding Design
The scaffolding is erected to RapidBuild technical drawings and specification.


Placeholder

Step Two


Ring Beam
The Ring Beam is laid around the inner leaf on top of the brickwork footing which consists of a single course of bricks at DPC level.


Placeholder

Step Three


Building Blocks
The Concrete or Thermal Blocks are built to joist height, the joists laid, a ring beam laid above joists and built to wall plate. Tie wires are installed at 900x450mm centres.


Placeholder

Step FOUR


RapidBuild Components
The RapidBuild Components are fitted to the scaffolding and tied into the inner wall structure. This gives total stability to the internal structure


Placeholder

Step FIVE


Cavity Closer
The Cavity Closers are installed and tied into the blockwork allowing additional strength to fit the window into the internal skin.


Placeholder

Step SIX

Poro Lintels
Poro-Cav Lintel features a unique ‘thermal break plate’ that aids the thermal performance of the wall. The inner leaf is supported through a standard box lintel whilst the outer leaf support comes from the uniquely designed outer lintel.



Placeholder

Step seven


Joist Ringbeam
The Ring Beam of coursing brick is laid above the joists as an additional Ring Beam to give extra stability and an accurate level to build the 3rd and 4th lift to wall plate.


Placeholder

Step eight


Roof Trusses
Roof Trusses are installed once the blockwork reaches wall plate and the wall plate is fitted.


Placeholder

Step nine


Fascias and Soffits
The Fascias, Soffit Boards and Barge Boards are fitted once the roof trusses have been fully installed. The soffits will be fitted leaving a 25mm gap to ensure the outer bricks can be laid up to them.


Placeholder

Step ten


Membrane (Roof)
The felt membrane and batten is laid on the roof once the trusses have been fully installed to ensure a waterproof layer.


Placeholder

Step eleven


Windows
The Window installation takes place once the blockwork, roof trusses and felt and batten have been completed.


Placeholder

Step twelve


Cavity Insulation
The Cavity Insulation is fitted to the blockwork with ease and ensures no mortar droppings are behind the panels.


Placeholder

Step thirteen


Membrane (Walls)
The breathable Membrane is fitted to the insulation with a spray adhesive to ensure an extremely high performance for air testing and a total waterproof barrier


Placeholder

Step fourteen


Roof Tiles
The Roof Tiles are installed once the trusses have been installed, felt & battened, fascias, soffits and bargeboards fitted.


Placeholder

Step fifteen


Face Bricks & Internal Trades
The face bricks are built following the line of the inner blockwork. The facing bricks can be laid when all internal trades are taking place allowing for a faster and better quality build. As the inner blockwork skin has been laid the outer facing bricks will require a much lower skilled brick layer as they have a building line to work to.

Benefits of our methodology.


Speed of Build

Cash Flow Advantage

Ability to Build in all Weather Conditions

Lower Skill Levels Required

Breathable Membrane

Tie Wires


Insulation

Windows

Potential HSE Claims

Scaffolding Visits

Quality of Brick and Blockwork

Less wastage